Route 152 over I-35

Miles Excavating, Inc.

Route 152 over I-35 Bridge Demolition

___________________________________________________________________________________________________________________________

​

​

Project Location: Liberty, Missouri

​

Demolition Dates: 05/31/2019-06/02/2019

​

Work Completed: Demolished, recycled, and hauled off the existing MO-152 bridge. Demolition started in the

evening on Friday and was finished in the early morning on Sunday. The demolition was completed before the expected deadline, which allowed MODOT to re-open the I-35 closure earlier than originally planned.

​

Testimonial from Miles Excavating:

​

" We went with Greg Bair Track Hoe Service for the MO-152 bridge demolition because they are the most qualified in town. We appreciated how they pre-loaded their work site with around 20 of their machines, and were able to go right to

work when the highway closure had begun. They worked

non-stop until the job was completed. Their preparation, time management, and around-the-clock dedication, allowed us to re-open the highway closure earlier than we had expected."

quote by:  John Conrad       

​

LINK TO MO-152 / I-35 PROJECT ARTICLE:

https://www.acppubs.com/articles/8428-missouri-152i-35-redesign-underway-in-kansas-city

​

​

PHOTOS TAKEN BY KLORISSA BOX

© 2018 by Greg Bair Track Hoe, Inc.

  • GBTS Facebook
bottom of page